Respuesta corta
Ship before the slowdown, not before the holiday date.
Chinese New Year 2027 is on February 6, 2027. Packaging factories typically slow down in the weeks before the holiday as staff travel home, close for the holiday period, and return to full capacity gradually afterwards. The date that matters for your order is therefore the supplier's last pickup day, not February 6.
Ask every supplier, in writing, for four dates: last production day, last pickup day, reopening day and expected full-capacity day. Then plan your artwork, sample and production backward from the last pickup day.
Boundary: mainland China announces its official holiday arrangement separately, and each factory sets its own closure. This guide gives the planning method; confirm actual dates with your supplier and forwarder.
1 · Work backward
The pre-holiday packaging timeline.
Each milestone has to be finished before the next can start. Replace the durations with the lead times your supplier quotes for your exact box, finish and quantity.
Desplazarse horizontalmente para ver todas las columnas →
| Milestone | Must be done | Por qué importa |
|---|---|---|
| Artwork, dieline and structure final | Before the sample is made | Every later step waits on approved files; a late artwork change restarts sampling. |
| Pre-production sample approved | Before bulk materials are cut | Colour, fit, insert and finish are locked while the factory is still at full capacity. |
| Materials and special components booked | At sample approval | Specialty paper, magnets, foil, ribbon and inserts can run short before the holiday. |
| Bulk production and QC complete | Supplier’s quoted production time before the last pickup day | Ask for the quoted working days in writing, plus inspection and packing time. |
| Last pickup or ex-factory date | Confirmed by supplier and forwarder | Freight space and trucking tighten in the weeks before the holiday. |
| Restart and full-capacity date | Confirmed in writing | Production often resumes gradually; plan reorders and launches around full capacity, not the first working day. |
Use la anterior de dos fechas: la última recogida confirmada por proveedor y transitario, o la recepción requerida en almacén menos el plazo completo de entrega y margen. Luego retroceda por control de calidad, producción, materiales, envío de muestra, revisión y archivos. Use el lead time planner to calculate your own dates from the quoted durations.

2 · Reduce holiday risk
Five ways to protect a launch around Chinese New Year.
- Freeze artwork earlyLos cambios tardíos de texto, código de barras o color pueden exigir otra prueba o muestra y un calendario revisado.
- Approve one physical sampleLock board, wrap, finish, insert and colour target on a signed sample before the factory slows down.
- Book materials with the orderSpecialty papers, magnets, ribbons and foils can sell out before the holiday; confirm they are reserved.
- Split the order if neededShip a smaller pre-holiday batch for launch and schedule the balance for after full-capacity restart.
- Hold buffer stockCover the closure plus the slow restart weeks, especially for packaging tied to Valentine's Day or spring launches.
Agree the delivery basis early too: see the EXW, FOB, CIF and DDP guide for who books freight in each case.
3 · Send this now
What to send your supplier this week.
A complete brief lets the supplier confirm whether your order can still ship before the holiday.
- 01
Product and box details
Box style, internal size, product weight, insert, quantity per SKU and number of SKUs.
- 02
Artwork status
Final or draft artwork, dieline status, Pantone targets, foil and embossing areas.
- 03
Required date
Date the packaging must arrive, destination and preferred delivery basis.
- 04
Ask for the four dates
Last production, last pickup, reopening and full-capacity dates, confirmed in writing. Use the Plantilla RFQ to keep quotes comparable.
Preguntas del comprador
Chinese New Year packaging FAQ.
Closure dates vary by factory and region; always confirm them with your supplier.
Verifique por separado el calendario y las fechas comerciales.
Los días laborables no son días naturales. Convierta cada etapa según el calendario laboral y los cierres del proveedor responsable antes de introducirla en el planificador.
Observatorio de Hong Kong: calendario lunar de 2027. Datos de empresa y condiciones de pedido.
Cajas de papel personalizadas: mínimo de 1.000 por diseño; muestras en unos 7 días laborables; producción en 25–35 días laborables tras aprobar la muestra. Transporte aparte. Otros componentes y formatos complejos requieren presupuesto específico.
Hoja de planificación
Asigne una fecha confirmada y un responsable a cada hito.
Descargue el CSV vacío en inglés, registre fechas y supuestos con su proveedor y transitario y pegue los hitos clave en la solicitud. Un campo vacío significa sin confirmar; la hoja no reserva capacidad ni transporte.