Réponse courte
Ship before the slowdown, not before the holiday date.
Chinese New Year 2027 is on February 6, 2027. Packaging factories typically slow down in the weeks before the holiday as staff travel home, close for the holiday period, and return to full capacity gradually afterwards. The date that matters for your order is therefore the supplier's last pickup day, not February 6.
Ask every supplier, in writing, for four dates: last production day, last pickup day, reopening day and expected full-capacity day. Then plan your artwork, sample and production backward from the last pickup day.
Boundary: mainland China announces its official holiday arrangement separately, and each factory sets its own closure. This guide gives the planning method; confirm actual dates with your supplier and forwarder.
1 · Work backward
The pre-holiday packaging timeline.
Each milestone has to be finished before the next can start. Replace the durations with the lead times your supplier quotes for your exact box, finish and quantity.
Faites défiler horizontalement pour afficher toutes les colonnes →
| Étape | Must be done | Pourquoi c'est important |
|---|---|---|
| Artwork, dieline and structure final | Before the sample is made | Every later step waits on approved files; a late artwork change restarts sampling. |
| Pre-production sample approved | Before bulk materials are cut | Colour, fit, insert and finish are locked while the factory is still at full capacity. |
| Materials and special components booked | At sample approval | Specialty paper, magnets, foil, ribbon and inserts can run short before the holiday. |
| Bulk production and QC complete | Supplier’s quoted production time before the last pickup day | Ask for the quoted working days in writing, plus inspection and packing time. |
| Last pickup or ex-factory date | Confirmed by supplier and forwarder | Freight space and trucking tighten in the weeks before the holiday. |
| Restart and full-capacity date | Confirmed in writing | Production often resumes gradually; plan reorders and launches around full capacity, not the first working day. |
Retenez la plus précoce de deux dates : le dernier enlèvement confirmé par le fournisseur et le transitaire, ou la réception requise en entrepôt moins tout le délai de livraison et la marge. Remontez ensuite le contrôle qualité, la production, les matières, le transport d’échantillon, la validation et les fichiers. Utilisez le lead time planner to calculate your own dates from the quoted durations.

2 · Reduce holiday risk
Five ways to protect a launch around Chinese New Year.
- Freeze artwork earlyDes modifications tardives du texte, du code-barres ou des couleurs peuvent exiger une nouvelle épreuve ou un nouvel échantillon et un calendrier révisé.
- Approve one physical sampleLock board, wrap, finish, insert and colour target on a signed sample before the factory slows down.
- Book materials with the orderSpecialty papers, magnets, ribbons and foils can sell out before the holiday; confirm they are reserved.
- Split the order if neededShip a smaller pre-holiday batch for launch and schedule the balance for after full-capacity restart.
- Hold buffer stockCover the closure plus the slow restart weeks, especially for packaging tied to Valentine's Day or spring launches.
Agree the delivery basis early too: see the EXW, FOB, CIF and DDP guide for who books freight in each case.
3 · Send this now
What to send your supplier this week.
A complete brief lets the supplier confirm whether your order can still ship before the holiday.
- 01
Product and box details
Box style, internal size, product weight, insert, quantity per SKU and number of SKUs.
- 02
Artwork status
Final or draft artwork, dieline status, Pantone targets, foil and embossing areas.
- 03
Required date
Date the packaging must arrive, destination and preferred delivery basis.
- 04
Ask for the four dates
Last production, last pickup, reopening and full-capacity dates, confirmed in writing. Use the Modèle RFQ to keep quotes comparable.
Questions de l'acheteur
Chinese New Year packaging FAQ.
Closure dates vary by factory and region; always confirm them with your supplier.
Vérifiez séparément le calendrier et les dates commerciales.
Les jours ouvrés ne sont pas des jours calendaires. Convertissez chaque étape selon le calendrier de travail et les fermetures du fournisseur responsable avant de la saisir dans le planificateur.
Observatoire de Hong Kong : calendrier lunaire 2027. Informations sur l’entreprise et les commandes.
Boîtes en papier sur mesure : minimum de 1 000 par modèle ; échantillons en environ 7 jours ouvrés ; production en 25–35 jours ouvrés après approbation. Transport séparé. Autres composants et formats complexes : devis spécifique.
Feuille de calendrier
Attribuez une date confirmée et un responsable à chaque jalon.
Téléchargez le CSV vierge en anglais, renseignez les dates et hypothèses avec votre fournisseur et transitaire, puis collez les jalons clés dans votre demande. Un champ vide reste non confirmé ; cette feuille ne réserve ni capacité ni transport.